GUPCO's Mega Rehabilitation Project, Morgan 36 Platform

"The project aims to the Rehabilitation of BP offshore facilities including steel structural platforms, topside facilities and subsea pipelines."

Red Sea, Egypt

Table of contents

Sectors

  • Oil & Gas

Expertise

  • Electrical
  • Mechanical
  • HVAC

Capabilities

  • Engineering
  • Procurement
  • Construction

Clients

  • BP [British Petroleum]
  • GUPCO [Gulf of Suez Petroleum Company]
  • ENPPI [Engineering for Petroleum and Process Industries]

Project Overview

"The project aims to the Rehabilitation of BP offshore facilities including steel structural platforms, topside facilities and subsea pipelines."

The rehabilitation initiative was designed to extend safe operational capacity for an additional 25 years across the entire offshore complex.

Location

Ras Shoukar, Red Sea, Egypt

Key Stakeholders

  • Owner: GUPCO / BP
  • Contractor: Enppi (Engineering for Petroleum and Process Industries)
  • Consultant: Enppi

Facility Scale

  • 9 major complexes and 69 satellite platforms
  • 119 total platforms
  • 400 wells
  • 1,600 km of subsea pipelines

Argonaut's Scope

Design, fabrication, supply, and installation of HVAC and pressurization systems including:

  • Air-cooled packaged air conditioners
  • Explosion-proof motor control centers and fans
  • Fire and smoke dampers
  • HVAC control systems
  • AISI 316L grilles and diffusers
  • Ductwork with internal/external insulation